2025-2026 Capital works
Our capital works program continued to focus on renewing and improving infrastructure to meet the current and future needs of our community.
In 2025–26, we spent approximately $25.39 million on our capital works program – a significant investment in infrastructure across Darebin.
John Hall Reserve Pavilion redevelopment
We completed the $2.8 million redevelopment of the John Hall Reserve Pavilion, replacing the ageing pavilion with a new accessible and inclusive community sporting facility. The previous pavilion had reached the end of its useful life and no longer met contemporary standards for multi-gender sport, limiting opportunities for participation and growth.
The new pavilion includes gender-inclusive player and referee changerooms and amenities, a larger social and function space, kitchen and kiosk facilities, accessible public amenities, storage and a first aid room. The new facilities support increased participation, particularly among women, girls and junior players.
The larger social spaces and improved kitchen and kiosk facilities also give clubs more opportunities to host activities and generate revenue, supporting their long-term sustainability.
Project cost: $2.8 million
KP Hardiman Reserve Pavilion redevelopment
We completed the $2.7 million redevelopment of the KP Hardiman Reserve Pavilion, providing new facilities for organised sport and broader community use.
The new pavilion includes gender-inclusive changerooms, publicly accessible amenities, community social spaces, a first aid room and dedicated storage areas. We developed the design in consultation with sporting organisations, Traditional Owners, key stakeholders and relevant Council teams.
The pavilion also includes solar power, water reuse systems, passive design features and energy-efficient electric services. Together with the recently redeveloped synthetic playing surface and upgraded LED sports lighting, the pavilion provides improved facilities at KP Hardiman Reserve and supports increased participation, particularly among women and girls.
Project cost: $2.7 million
Massey Avenue drainage upgrade works
We completed major drainage upgrade works along Massey Avenue to improve the local stormwater network and help address long-standing flooding issues in the area.
We installed more than 150 metres of new drainage pipes, ranging from 675 mm to 1,500 mm in diameter and upgraded sections of the existing drainage network to increase its capacity. We also constructed more than 10 new drainage pits to improve stormwater collection and connectivity.
The upgrades improve how stormwater is managed during heavy rainfall, helping reduce the risk of flooding, overflows and water accumulation in the area.
Project cost: $365,000