Project Location Suburb Start Completion Contractor Project value
Dole Reserve, Reservoir - wetlands
Read summary
Location Dole Reserve Suburb Reservoir Start 10/01/22 Completion 30/09/22 Contractor Entracon Project value$3,500,000
Construction of a wetland, sediment pond, GPT and harvesting tanks
High Street & Broadway, Reservoir - urban node
Read summary
Location High St & Broadway Suburb Reservoir Start 28/03/22 Completion 15/07/22 Contractor Rapid Paving Project value$250,000
Street Scape, footpath reconstruction and bespoke furniture at corner of High St & Broadway Reservoir
Spring Street, Reservoir - footpath reconstruction
Read summary
Location Spring St Suburb Reservoir Start 21/02/22 Completion 15/07/22 Contractor Rapid Paving Project value$250,000
Reconstruction of Footpath along Spring St from Cleeland to Kenilworth
Victoria Street Preston - rehabilitation
Read summary
Location Victoria St Suburb Preston Start 07/03/22 Completion 20/07/22 Contractor Petrolo Construction Project value$860,000
Reconstruction of Victoria St between Neale St and Raglan St including kerb & crossovers

The list above relates to upgrades to roads and drains.

Further Information:

Assets & Capital Delivery
Email: engineering@darebin.vic.gov.au